Table of Contents
11 Executive Summary|910|II | Background|910|III | Implementation of PRTF's Recommendations|910|IV | Incomplete PRTF Recommendations 10
A | Recommendation 7 10
B | Recommendation 19 11
C| Recommendation 28 12
V | Conclusion 12
Appendix A 14I | Executive Summary
In 2015, the Chicago Procurement Reform Task Force (PRTF), comprised of the City of Chicago and a number of its sister agencies, undertook a six-month project to identify opportunities for local governmental entities to implement best practices for public contracting. PRTF reported its findings and made 31 recommendations. Pursuant to an intergovernmental agreement (IGA), the entities involved (collectively, the Participating Members) launched a responsive reform process. Over the past seven years, they have completed work on 28 of the 31 recommendations made by PRFT. The three recommendations which have not been implemented were critical to PRTF's mission and goals: to create a single website providing contracting information and guidance from all Participating Members; adopt best practices for routine audits of procurement processes, ideally using shared services to that end; and implement a universal procurement system—a single point of entry for posting and responding to all Participating Members' contacting opportunities.
In November 2022, a committee comprising Chief Procurement Officers of the involved agencies (CPO Committee) issued a "Close-Out and Status Report" announcing the termination of the PRTF project. Regarding the three incomplete recommendations: (1) the CPO Committee states the website has launched, but it has not; (2) the Committee asserts without substantiation that the Participating Members have done as much as they can to implement effective audit practices; and (3) the Committee concludes that a universal procurement system is unachievable due to lack of funds and differing governance rules and regulations, but does not explain how and why the considerable efforts on this front described in its prior public reporting have failed to come to fruition.
In accordance with its legal mandate, the Office of Inspector General (OIG) publishes this independent evaluation of the progress of the Participating Members' implementation of PRTF's recommendations.II | Background
The Chicago Procurement Reform Task Force (PRTF) convened in May 2015. The City's Chief Procurement Officer (CPO) and then-Inspector General co-chaired the initiative, which included the Chief Executive Officer, Executive Director, or Chancellor of six other local governmental bodies: Chicago Public Schools (CPS), the Chicago Transit Authority (CTA), the Chicago Housing Authority , (CHA), the City Colleges of Chicago (CCC), the Chicago Park District (Parks), and the Public Building Commission (PBC) (collectively, the Participating Members). PRTF was "tasked with developing recommendations to make procurement and contract management at the City and its sister agencies more uniform, efficient and cost-effective, while increasing accountability. Its goal was to distinguish successful practices, identify areas for improvement and promote a greater level of uniformity across City government and each participating sister agency."1
In November 2015, PRTF reported its findings, grouped into five categories representing what the Task Force deemed the essential principles of government procurement: competition, efficiency, transparency, integrity, and uniformity. PRTF also offered recommendations designed to advance these principles—a 31-point plan for refining and standardizing the Participating Members' procurement operations. The recommendations in the 2015 Report, provided below in Figure 1, fell into three categories: the first 15 (grey) were proposed for "immediate" implementation (i.e., by March 30, 2016); the next 12 (green) for "mid-term" implementation (by December 31, 2016); and last 4 (blue) for "long-term" implementation (in "2017 and beyond").
Figure l: PRTF Recommendations
fjl)mmeJSation #1-- CreafenaCommittee of the.P.articipafirfg;:Member.|' CPOs to rule'o'n ceftainjaplministrative , decisiobsfedcfressfdistaclesTo coordiratibn, aricHensure beskpracticesfacrosssthe. City abdjitsC; •sist.esagenci.es; ' "r, " ¦ •••'•' ' -v '>
Recommehfatiom#2: Charge the C.PO Committee withraddnessing the Task Force recommendatibns, tracking theii impl|mentatidh,:and jsSuihg-guaittgrjWpfpgressfeportSTc ¦ , . • ... .- . M
>* j. Recommendation #3 il^piiish minimum-standards::i5^hiclTall:Panfieipatihg;Membe'rs will publish theikanticipatedjfC sblffsource awards, receive publiciand vendocfeedback, and make decisions about whether a , -. < • •• "• ' ,if> ¦¦¦'¦ s.Qli;eitationis'necessary. • p..- :C , -imsi
^Recommendation1#^-: F)jr@:6r secure"pro b'6|fo servicesTrom-a lawtfirm to: (a)4dentify(cdntract;:provisiohs(tha!p:ould;.bei subject to standardization across Participating Members' templates, and draft uniform contract templates incorporating,the,required terms'of'the Participating.Members'; including:contract '"--f ^duration ahdfnumbefcdf renewals and (bV Whefeiappropriatefstandardize' solicitation documents issued by Participating Members and the documents required in response. 1 fc
. Recommendation #5 C; f Cbarde the-ChicagdfGbvernment IT. Cobrdinatidh'CommitteeTITCG], which consists of the.C.IOs; Ipf the ParticijaatingiMembersiywith identifying the.prpcuremedCrelated-systerTis thakcarFbe' Isharedlihd;i.e^to^'rj0int1y>'any deveJopji-Recommendation #.6.;;^ siPdst.ajLconfrgGfe^vendofsj'a'nd'subcp on-agency .website's in a'Uspr.-friendlysarid searchable format. !b.-
Recommendation Create an easily accessible website for venoors and the public that provides a single location for: all of the Participating Members' current procurement opportunity listings and other
1 City of Chicago, Procurement Services, hltos //www Chicago qov/citv/en/deDts/dps/provdrs/procurement-rcform-task- force.lnml (lasl accessed February 15, 2023)
1 u' • . ? . ' *.» ' . • *¦ procurement related information'subh as the buying plan, notices of award,, and.prequalified pools;- a'.list of-all'debarred'.vendors: and.all.d'urrent cpntradt^ vendor databases,.
Recommendation #8 Establish minimum disclosure requirements for subeplntf^ . 1 suipontractor informatiomonline.' w ¦
¦ Recommendation #9 Establish minimum standards for conducting due diligence of vendors before entering into a contract. ¦ -
life , . ' Recommendation #10 V,-'" * Establish uniform rules governing resojicitation.of contraetsidue to significant changes in scope or value.* • .*•> •• justa. - *. *»* - ¦,;* X,'**
::.Recommendation^#11 EvafuaWtlne-cbnsistency of MBE/WBE/DBE 'certification^c'eepted;by:Parti.Gipatihg Members
Recommendation;#12 ¦¦ ¦ . .- :sSS ' Implement the unifornrrcriteria and propepe§4oFevaluatihg Gqobl Fajth-EffSjrts regaling • requests for waivers of MBEA/VBE/DBE'gc^fthat are currently being developed and will be recommended b^theiGo^rnment Prc^ui^meht Compliane^Ppr^m.7'®,; ->•
iRecommendatidn #13 Requires'writtenvipUbliciylposfed protdsf process for eacSi^lipipating;''Member.
r. Reeommecid| tjon^ # 1 4. . Ex a m i melv/bTe t fner J^Pa rt i c i p a t i n g Members should suppFrilWtnFpge iriWatelavvdo eliminate :the' newspape'Pnotice requirementifoi:.contract solicitations.:^!?1?- # . -"- X .*'. .'
Recommendation^5 Establish'-a-process for infof^pon-shanpg^nd^llaboraricih among Partppating Members on personnel matters^such as professionalXeMopment efforts. andfrecruitnSent:.%^ :
Recommendation #16 Establish uniform standards based on best practices for approval of noncompetitive awards, - : :; including small purchase, emergency, and sole source. VFr
Recommendation #17 Develop a common electronic EebnomiCiDisclosure Statement system that: allows for the ' submission of uniform information for all Particioating Members' vendors and subcontractors; integrates disclosures and certifications into Participating Members' procurement databases; automates conflict checks and due diligence; and can be updated in real time. .
Recommendation #18 Establish a process for the use of joint pro-qualified vendor pools that recognizes the different statutory requirements applicable to Participating Members. .'FF"'v cF-fl
Recommendation #19 Develop best practices for routine audits of procurement functions and contract awards, and' evaluate use of shared services to perform this function. '
Recommendation #20 Require each Participating Member to create a comprehensive procurement manual for its staff that is user-friendly and available to the public. v y/i
Recommendation #21 Codify and provide training to Participating Members' employees on procurement rules and regulations, including appropriate authority, prohibited communications, and reporting obligations.
Recommendation #22 Develop universal programming for vendoroutreach and training. :
Recommendation #23 Develop uniform, minimum contract close-out procedures for use by all Participating Members. .
Recommendation #24 Develop minimum standards for project managers and other on-site review personnel to ensure vendor compliance.
Recommendation #25 Establish a process for information-sharing among Participating Members regarding poor performance, noncompliance, or wrongdoing of a vendor.
Recommendation #26 Seek to establish reciprocal debarment among Participating Members through the use of a debarment review board or another mechanism as permitted by. law.
Recommendation #27 Establish uniform practices, where permitted by law, to expand preferences for local vendors and support a workforce development or similar contract award preference.
Recommendation #28 Implement a universal procurement system that serves as a single point of entry for posting and responding to all Participating Members' procurement opportunities, and as a central repository for all contract and vendor information.
Recommendation #29 Identify compliance functions that can be shared among Participating Members, including MBE/WBE compliance activities, and establish a joint compliance field team.
Recommendation #30 Secure a pro bono study regarding the financial impact of the City's risk shifting contractual provisions. , AAA.-. . . A - AS':' AJT : ::
Recommendation #31 Evaluate the benefits: of center-led of consolidated procurement among the Participating \ Members. - #: T
Pursuant to an intergovernmental agreement (IGA) executed under the authority of an ordinance passed by City Council and approved by then-Mayor Rahm Emanuel in January 2016, included here as Appendix A, the Participating Members implemented PRTF's Recommendation #1 by creating a committee of their CPOs—the so-called "CPO Committee"—and charging it with addressing the Task Force's recommendations, tracking their implementation, and issuing quarterly and annual reports. The IGA also directed the Participating Members to implement Recommendation #5 by establishing a committee of their Chief Information Officers (the Chicago Government IT Coordination Committee, or ITCC) to manage the technical aspects of the process of implementing PRTF's recommendations.
The Participating Members agreed to issue four reports per year: quarterly reports within 14 days after the end of March, June, and September, and an Annual Report within 60 days after the end of each calendar year, beginning with 2016. The IGA provided for an initial five-year term (2016 through 2021) with two automatic extensions of two years each (2021 through 2023, and 2023 through 2025) unless all Participating Members agreed in writing not to extend the project, and stated that the Participating Members would "participat[e] annually in a public hearing of City Council to discuss the [PRTF] Annual Report."2 Finally, the ordinance directed the Office of Inspector General (OIG) to issue—within 90 days following the issuance of each Annual Report—an independent evaluation of the Participating Members' implementation of PRTF's recommendations.
In 2017, 2018, and 2019, OIG issued these Progress Reports in late spring, following the March issuance of the PRTF Annual Reports for 2016, 2017, and 2018, respectively. In 2020, the COVID- 19 pandemic disrupted this timeline. The CPO Committee was unable to issue the 2019 Annual Report until June 2020. The pandemic likewise disrupted the issuance of the 2020 quarterly reports. Due to these and other related operational challenges, OIG did not issue its 2020 Progress Report until December.
In March 2021, OIG and the City's Department of Procurement Services (DPS) proposed to the Mayor's Office that the City—in consultation with the CPO Committee—amend the IGA to require a final consolidated report declaring a refreshed commitment to, and setting a calendar for, addressing the open PRTF recommendations. The Mayor's Office agreed with the proposal, but indicated it would not seek any changes until 2022. The CPO Committee informed OIG it would therefore return to the required reporting schedule in 2021. Plowever, the Committee issued only one report that year: the 2020 Annual Report, in October. The Participating Members' delay in filing this report continued a historic trend of inconsistent compliance with the reporting schedule. Again, the IGA required three reports in 2016 and four in each subsequent year. Thus, the Members should have issued 27 reports from 2016 through 2022, inclusive. Ftowever, they issued only 17: three in 2016, three in 2017, three in 2018, three in 2019, two in 2020, one in 2021, and one in 2022. Rather than issuing a Progress Report assessing the seven-month-late 2020 Annual Report, OIG addressed the situation in its Report for the Fourth Quarter of 2021.
2 To date, three such hearings have occurred on July 14, 201 7 and September 18, 2018 (before the now-defunct Committee on Workforce Development and Audit), and on October 7, 2019 (before the Joint Committee on Contracting Oversight and Equity and Ethics & Government Oversight)The CPO Committee did not issue any reports in the first 10 months of 2022. When the Mayor's Office reengaged with OIG and DPS in August 2022, DPS expressed an intention to issue what it described as a "final, close-out report" on PRTF. On October 11, 2022, DPS informed OIG that it had scheduled a meeting for October 19, 2022, to discuss this so-called close-out report with the other Participating Members.
On October 14, 2022, as required by the Municipal Code of Chicago, OIG published its Quarterly Report for the third quarter of 2022. Therein, OIG noted that the CPO Committee's most recent Annual Report (covering 2020, issued in October 2021) acknowledged substantial efforts, remaining to address the PRTF recommendations. OIG acknowledged the Participating Members' authority to opt out of the second extension of the IGA and end the PRTF project in early 2023, and explained that in the event they chose to exercise this option, OIG would issue a report assessing the Members' fulfillment of the recommendations. OIG suggested, however, that given the work remaining as of October 2020, the Members might choose to continue the project through the entire nine-year period (2016-2025) contemplated by the IGA as potentially necessary to achieve the recommended reforms.
On November 23, 2022, the CPO Committee transmitted to OIG, Chairwoman Pat Dowell of the City Council Committee on Budget and Government Operations, and Chairman Jason Ervin of the Committee on Contracting Oversight and Equity a document, dated "October 2022," more than a year before it was transmitted, titled "Close-Out and Status Report of The Chicago Procurement Reform Task Force" (Close-Out Report).3 The report's cover memorandum stated: "It has been determined by the participating members that the work of the PRTF is complete to the extent that all feasible recommendations could be and have been implemented. To that end, this will be the final report submitted." Likewise, the report itself stated: "At the final meeting of the PRTF which occurred on October 19, 2022, all Sister Agencies concluded that any recommendations partially implemented [sic] and could not be fully implemented were due [sic] legal governance matters, technological, or financial resources." As required, OIG publishes this assessment within 90 days of the issuance of that report.
Over the past seven years, the Participating Members have made considerable progress toward realizing the vision of PRTF. They have completed work on 28 of the 31 recommendations, either through implementation or determination after thorough consideration that particular recommendations are impracticable or will not actually achieve the benefits contemplated by PRTF.
Notably, however, substantial areas of potential reform have gone unaddressed or remain incomplete—including some of PRTF's most significant and potentially impactful recommendations. Specifically:
• The "easily accessible website for vendors and the public that provides a single location for: ¦ all of the Participating Members' current procurement opportunity listings and other procurement-related information" prescribed by Recommendation 7 is not currently accessible, months after it was to become available.
3 It is unclear whether the date on the transmitted report was an error Implementation of the Recommendations of PRTF• Recommendation 19, to "[d]evelop best practices for routine audits of procurement functions and contract awards, and evaluate use of shared services to perform this function," has not been implemented. The CPO Committee evidently determined implementation is infeasible, but offers little meaningful explanation for that determination.
• The CPO Committee has abruptly abandoned its efforts to implement one of the capstone reforms proposed by PRTF—Recommendation 28, calling for the Participating Members to "implement a universal procurement system that serves as a single point of entry for posting and responding to . procurement opportunities, and as a central repository for all contract and vendor information." Past reporting by the Committee had described multiple steps taken by the Members, in two phases, toward fulfilling this recommendation. The first phase—which, according to the Committee, was completed in 2021—"documented existing processes and legal or regulatory requirements and made recommendations for business process or other changes that would need to be implemented across all agencies to support a single system," and stated that the "ITCC [would] determine whether a single system or common components will be best." Close-Out Report at 10 (citing PRTF 2020 Annual Report). Phase 2 was to "implement the single system or common components across all agencies in approximately two years from the start," with the caveat that "the BPR [business process reengineering] [would] assist in refining the Phase 2 timeline, elements, and estimated budget." Id. Now, hovyever, the Committee concludes that "a universal procurement system is not achievable across all agencies" because "funding resources prohibit a universal system" and "differing governance rules and regulations prevent a broad-based universal system absent an authorizing change from the governing body for each agency." Id. at 11.
Unless and until the Participating Members launch a consolidated website announcing procurement opportunities and providing related supporting information developed throughout the project— thereby implementing recommendations 7 and 28— the core values of efficiency and uniformity identified by the Task Force remain unrealized. And without rigorous efforts to evaluate, reform, and (as possible) standardize processes for auditing the Members' procurement operations, there is no way to monitor the improvements resulting from the PRTF initiative and ensure they are meaningfully sustained.III | Implementation of PRTF's Recommendations
Figure 2 below illustrates the history of the Participating Members' progress in implementing PRTF's , 31 recommendations, from the project launch in January 2016 through November 2022. For each recommendation, Figure 2 shows both the implementation status reported by the CPO Committee and OIG's evaluation of the implementation status in the immediately following Progress Report. For purposes of clarity and consistency with previous progress reports, OIG uses the term "partially completed" to describe the recommendations classified by the CPO Committee as "outstanding" in their Annual and Quarterly Reports.4
Figure 2: Implementation Status of PRTF's Recommendations Over Time
Rec. No. PRTF 2016 Annual Report (3/2017) OIG First Annual Progress Report (5/2017) PRTF 2017 Annual Report (3/2018) OIG Second Annual Progress Report (5/2018) PRTF2018 Annual Report (3/2019) OIG Third Annual Progress Report (6/2019) PRTF 2019 Annual Report (6/2020) and 022020 quarterly report (10/2020) OIG Fourth Annual Progress Report (12/2020) PRTF Close-Out and Status Report (11/2022)
#1 Completed Completed Completed. S^llefe! Completer ;'5*eted* , Completed :.'.*Carnpleted:::",;!^|
1/2 Onqoinq ¦ Completed Completed Siompletedil IfCmmpietedSl Bfbompieted:5:," ¦¦"kC^Cleted;5*. Completed , Completed ;.,'.i
#13 ^Completed'; " ' //SPA/;' : Completed ' ¦¦ . ¦. TTtT;:; Completed. Illllimrlillll iBIlrriconsistenf;.,-. ¦¦ implementation - '«•. Completed4',. Completed'? '* <">¦ ' J'.fS!
#4 Ongoing Partially completed Partially completed •. Partially . mompletedi# ifcQ§II T . .Partially.'- . & . : I-; tf' . : completed , a,. ;.Atdmpifeled ¦' Completed. "Completed ,|
115 Ongoing ... Partially . completed Completed mm jj||omi^ed *• ' Completed". ¦ ¦ ¦ , 1:11-: EE 'Completed jp Completed.**' ¦v.: - . .Completed;;.,! J?' . we;.* • t.M-
116 ¦¦-w&g&'T' ' .^ngoing.- , Partially completed . Completed: ¦ ¦ ¦ :-M smm piled , Inconsistent :i: implementation * ¦ / Completed * * C'odtpleted T.";',
ni Ongoing'": Partially completed. Partially5 completed , Partially ^completed it|9||Partial!y. Bcomplefed" Partially, completed ;S8f ^^^Rartially '' ii^onripieted b Partially:. Sf«'" completed ¦.vT, Partially .'fcompleted
#8 j:Cdmpleted;i- ¦ TTTT: Completed. Completed. "fpietbf Piled"; Inconsistent " ' implementation " . Completed' "Completed-"^
#9 Completed .¦» ' .>:• * Completed .¦¦¦Cdmpietedi • •• ^completed. Completed . fRaifially^Jt; *T ' completed ®°#eted '¦ Completed 'Completed, j...
if 10 kCompiet'edS; ^Completed* Completed:. ;** Completed WMSMFr.&Mk-.,.: P^ed-T :, Inconsistent "iimplementation ^^pled :'"-; Completed . *,T'Cornp!etedb "*
/in ?4- Comptetsdsx? : ' ' < M T Partially completed . Partiajly completed ¦ifkPaftialJy'' completed Completed:; *. Completed?*" Completed '¦ i.: Completed Cpmpleted'-**'';
;M2 *•• • ^.Completed^ • Completed ¦ TTTE ... Completed, Completed ¦ jGompleteciyi Inconsistent, implementation. ¦¦ ikGorfipleted-":. 4 * TEE Completed. '?; Completed
1113 Completed Completed Completedr ^ompleteciM HCompieted: ' ' CdhTplete'S^ ^Completed ¦' Completed ¦ Completed i
t: 14 ...Completed- Completed '¦ Completed! IIGompleleclf" fi'SSdmpleted "•. Completed®. Completed Completed . 'Completed k '
1115 Ongoing.:. • -'mmmz-'-'. Partially completed Partially ^completed:? partially,M P^mpletfedE IfEdmplefed'v Cdmpiet'edjS® SitCSmpleted : • M'ttm' ;:IT Completed . T'Gomple1;':l
1116 sCompleted ^Completed j IW^31 5 Inconsistent implementation ^^^mpleted- Completed . Completed !¦
1117 ; Ongoing*5'1 Completed Ongoing '•'•.'CSV •• .Partially 'completed ^'Ongoing-. ¦ :Partiajly; completed, v* : k Partially ^completed'i;- Partially'- .- SScomptetech*. »:«#18 Partially completed- Paftialjy compietedC Partially Eli*''J: , ¦^completed.;.; "-'¦'Partially "T completed ¦ ; ;¦ Partially' ¦* completed. " imSs- 'F : niCdrripleted., r ? , • . Completed —. Completed - ¦
¦' In its close-out report, the CPO Committee places Recommendations 4, 9, 18, and 20 under the category "Outstanding." However, as shown in the table, in the past, it has categorized these recommendations as Completed, and the content of the close-out report related to the recommendations confirms that status. The Committee does not explain this inconsistency
#19 Ongoing Partially. . compllted! ftPjftially®.!- "essssts^ Partially ! completed^ i^Paftidllv *' Wlfed"r :*•. Partially?;; . ;C i completed;. r i-'PaHiallfm,',:;? completed'... '¦ Pcompletediii -'- ' Partially 3 ¦'.completed;' •••
#20 Ongoing. Partially completed! ^completed; ^"^tjaliy1"' .completedlf ^SPartialjy' ©COT^leted - : . f Paftiallyf's* ' completed . • Completed !' -j Completed',
#21 ^OngoingSfe SOditipldtedi Completed: ^'CdrhpletedS Completed -. ¦-. Cofnpleted Completed GmCbrfipletedi;, ¦ - Completed
#22 Onqoinq -* i'Sompletedf Completed: Completed!;* incompleted, h- it. Completed ' Complete-: iS§-.Compiefec! '¦".'.Completed;^
#23 |P'*1 Jfcompleted'- T>:r. Completed Completed ¦¦¦ 'Completed.;; Inconsistent implementation Completed SS:-. '• Completed Completed ,V
#24 fcpngdingvy ""PattiajlyC- completed. ' Completed. ¦ iiiaiiliili9 ^Inconsistent ' ^implementation Completed ' . Completed completed/ils
#25 ^0rigqing\5-- Partially' completed ¦ i-Pattiallyi-.'i" completed ^Partially , ¦ '^^feted ¦ .,;Cgmplete^ ^.C^npiejedi1-;1''. incompleted-'.'1" 1 ? l<(rrp/ - - Completed- ¦ "/w^ompteted-'^t-r;
#26 ;.--.Qngoing^ Partially;;., ^completed Completed (impartially-. ¦ completed . IpilnGohsistent - implementation ¦ ;^orpp|pted ¦ f. Completed;:.- •i., " Completed-;;;;
#27 ¦ Completed iCornpietecil rCompleted Completed'.; ^©ompleted,# VciCompieti P®:6onipleted™,ni sin Completed ¦ 'i ;Completed.'.;X;'
#28 i#fddfessed.* Not yf-i-y- be*quh';- .n:Ongoing, Partially • ¦¦ completed .''y's' , *.r -;,-.:,iOngoing':.-'' ;; ., ^aftiallj^^ completed ... Partially ' -'-i '¦** completed ; ' Partially completed 'Paffialiy-'i!Ss -aBB^completed
#29 ¦ i addressed# : Not-yet;.-' beq'uh'r1'- ' Ongoing . !* Partially completed - v.'fenptel&l,'. . Completed . ^Completed',' ; ¦ - Completed .v
#30 Mp addressed v'; Nofyet"-' bequrv1 - ¦Ongoing Partially : completed Simple,3 ™-'Con^leted!;.' -,-'"Completed; - Completed n'-^^rhpletedii^i-
#31 Not ' teddfessed'. Not yet ^bllfanip --Partially® ¦'c'dfhpleteall I§Sen9 :. Eiaftiajly,. . completr } - Completed ... .- Completed 1 i'jjllbmpleted'' *
IV | Incomplete PRTF Recommendations
At the time of the issuance of its self-styled close-out report in November 2022, the CPO Committee had failed to implement three of PRTF's recommendations. Each is detailed below.
Recommendation 7 | Create an easily accessible website for vendors and the public that provides a single location for: all of the Participating Members' current procurement opportunity listings and other procurement related information such as the buying plan, notices of award, and prequalified pools; a list of all debarred vendors; and all current contract and vendor databases.
The CPO Committee-reports that Recommendation 7 is "Partially Completed." While the CPO Committee describes efforts made to build a website responsive to Recommendation 7, no such website is available as of this writing. OIG's assessment, therefore, is that Recommendation 7 is Not Completed.
The CPO Committee states:
During 2020 and 2021, the ITCC representatives, in conjunction with the City's consultant Electronic Knowledge Interchange (EKI), designed and built the Chicago Procurement Information web site to comply with this recommendation. The ITCC decided to deploy the web site with the available data of the participating agencies—COC, Park District and CTA. Other participating agencies (PBC, CHA,
CCC and CPS) are to add their data as it becomes available.
The consolidated site, Chicago Procurement Information, will be hosted by the City at . The site features a consolidated opportunity listing and allows users to sign up for notifications of opportunities by interest area, a consolidated list of awarded contracts, the City.of Chicago Consolidated Buying Plan, debarred vendors, and agency procurement procedures
The City's Assets, Information and Services (AIS) Department, through its staff and consultant EKI, will support the consolidated web site and onboard additional participating agencies as their data becomes available.
At [the time of the] Close-Out Meeting on October 19, 2022, CTA and the City had fully implemented the above recommendation. CPS was in the process of implementing the recommendation but is overcoming technical formatting matters prior to implementation. CHA, CCC, [Parks], and the PBC committed to advocating for additional resources to fully implement this recommendation. At the Close-Out Meeting, all participants concluded that the ITCC continue to meet to monitor the progress of the implementation of this recommendation.
According to the CPO Committee, httpsV/procurementinfo.Chicago.gov was "scheduled for a soft launch in August 2022 and [to] go live in September 2022;" the site would "go live wilh the City,Park District, and CTA information;" and "Park District opportunities and awards [were] anticipated to be available after go-live."
As of February 20, 2023, however, the website is inaccessible. The following is displayed at its address:
r .«i p, x •+
C o prc